Skatepark gets $50,000 from Alberta Blue Cross, construction resuming this spring

Skatepark gets $50,000 from Alberta Blue Cross, construction resuming this spring

Construction is expected to resume in April once the frost melts and last for seven weeks until being completed in June.
Jasper looking into loosening restrictions for temporary housing, laydown areas within townsite

Jasper looking into loosening restrictions for temporary housing, laydown areas within townsite

Residents and contractors have been pushing local officials to make more land available for in-town contractor camps, interim residences and laydown areas.
Jasper Aquatic Centre reopening delayed by several weeks

Jasper Aquatic Centre reopening delayed by several weeks

During the wildfire-related delays to the recreation facility renovations and subsequent cleanup, the pool suffered damage to the basin coating while being pressure washed, causing a delay of two-to-three weeks.
Jasper council gets update on interim housing, rebuild prep

Jasper council gets update on interim housing, rebuild prep

Utility serving is ongoing for the land parcels within the townsite allocated for interim housing.
Alberta government promises 250 modular homes for Jasper residents displaced by wildfire

Alberta government promises 250 modular homes for Jasper residents displaced by wildfire

“When people have a place to call home, they can better cope with all of life’s pressures and challenges.”
Construction work will continue at recreation facilities until December

Construction work will continue at recreation facilities until December

The wildfire temporarily halted work and necessitated additional cleaning, particularly in the Aquatic Centre. After remobilizing at the end of September, Carlson Construction resumed activities.
Jasper begins site servicing for interim housing

Jasper begins site servicing for interim housing

Interim housing will be located at the northeast end of town, along Connaught Drive adjacent to the future RCMP detachment and on a site called 2B just south of Highway 16.
Jasper planning to undertake mass debris removal following wildfire

Jasper planning to undertake mass debris removal following wildfire

The Jasper Recovery Coordination Centre is working with the Insurance Bureau of Canada to get more information out to the public about debris removal.
Feds plan to give Jasper planning and development authority to help with rebuild

Feds plan to give Jasper planning and development authority to help with rebuild

"By enabling the transfer of planning and development authorities to the municipality, it will make it possible to give the town of Jasper and businesses and residents more say to shape the future of the town."
Connaught affordable housing project proceeding despite wildfire

Connaught affordable housing project proceeding despite wildfire

"Understanding the impact of the Jasper Wildfire Complex on local housing, stakeholders are committed to the project and recognize the importance of moving it along quickly to address community needs."